Ten Mile Road from Evergreen Road to Greenfield Road Improvement Project


June 25, 2024

share this on  Facebook   Twitter   Email

10 Mile Road, Evergreen Road to Greenfield Road Improvement Project

LOCATION:  Ten Mile Road, Evergreen Road to Greenfield Road in Southfield.

PROJECT DETAILS:

The project cost is $5.25 million and is mostly funded with federal money with the RCOC providing match dollars.  

The 1.9-mile project includes:

  • Remove and replace sections of concrete.
  • Remove and replace concrete curbs and gutters.
  • Americans with Disabilities Act (ADA)-compliant ramps and crosswalks.
  • Traffic signal improvements at the Santa Barbara and Pierce intersections. 
  • Minor drainage improvements.

The work will be done on sections of 10 Mile Road that were not concrete patched in 2019.  

CONTRACTOR/TIMELINE/TRAFFIC INFORMATION:

CONTRACTOR:  Dilisio Contracting Inc. of Clinton Twp.

CONTRACTOR WEBSITE: https://www.dilisiocontracting.com/

START DATE: July 8

END DATE:  Fall

TRAFFIC INFORMATION: Ten Mile Road will remain open to two-way traffic during the work. There will be some side street approach closures to Ten Mile Road. Business access maintained.


ADDITIONAL INFORMATION:

For questions or comments, call 877-858-4804 or email dcsmail@rcoc.org