SECTION 35 – PHASE II
START: July 2021
COMPLETION: November 2021
$4.6M investment funded by the Water & Sewer Bond Fund and the Road Bond Fund
Work includes:
- Water main replacement including upgrading 6” mains to 8” mains
- Small amounts of storm sewer installations
- Rehabilitation of asphalt streets by pulverizing existing asphalt and topping with 4” of a new asphalt road surface
- Approaches replaced only when impacted by construction
Traffic impacts:
- Generally, roads are open during construction with minor delays
Other items of note:
- Mail delivery and garbage collection should continue normally
- Water service can be expected to be interrupted about 3 times during construction; advance notice will be provided; water service will always be re-established by the end of a work day, if contractors are gone and your water isn’t back on please call or email the project team