Section 35 – Water Main Replacement Phase II

Content

SECTION 35 – PHASE II

START: July 2021

COMPLETION: November 2021

$4.6M investment funded by the Water & Sewer Bond Fund and the Road Bond Fund

Work includes:

  • Water main replacement including upgrading 6” mains to 8” mains
  • Small amounts of storm sewer installations
  • Rehabilitation of asphalt streets by pulverizing existing asphalt and topping with 4” of a new asphalt road surface
  • Approaches replaced only when impacted by construction

Traffic impacts:

  • Generally, roads are open during construction with minor delays

Other items of note:

  • Mail delivery and garbage collection should continue normally
  • Water service can be expected to be interrupted about 3 times during construction; advance notice will be provided; water service will always be re-established by the end of a work day, if contractors are gone and your water isn’t back on please call or email the project team